Quality Control — Engineering Maintenance

Preview
This guide is a preview for review. It is not yet approved for publication.
Engineering MaintenanceNZ and AUEnterpriseCustomer package, 20 Nov 2026
Download PDFThe full guide is in the PDF. This page summarises it so you can search and read on a phone.

How quality control works​

Requirements → Trade pack → Job quality scope → Job quality plan → Inspections & tests → Nonconformances → Quality release → Job Quality Report PDF.

Hold points must be accepted before work goes past them; witness points invite someone to attend; review points check documents or competence. The person who accepts an inspection or approves a plan can't be the person who did it.

Why every trade pack shows Draft​

The library ships 50 packs per jurisdiction (NZ, VIC, NSW, QLD, WA, SA, ACT) as drafts on purpose: their requirements still say Unselected edition, many lines say DRAFT criterion for domain review, and nobody has a reviewer appointment yet. Activate only the packs for work you really do, after a competent person reviews them.

Activate a trade pack​

  1. Give the role: Settings → Users → the reviewer → Quality Control: Requirement reviewer.
  2. Record the appointment: Quality Control → Administration → Reviewer appointments → New (user, company, jurisdiction, valid from / until, verification reference).
  3. Activate the requirements first: Quality Control → Planning → Requirements; set the actual edition, effective date, source and evidence, then Review and activate.
  4. Review the pack: Planning → Industry Templates (Quality Trade Packs). Replace DRAFT criterion… text, set the sampling basis, fill the Domain validation tab.
  5. Review and activate the pack. To change it later, use New revision.

Signing on a job also needs a Quality operation appointment for that job (Administration → Quality operation appointments).

Use it on a job​

  1. Quality scope tab on the job: choose the actual Quality work site.
  2. Use pack from the suggestions (or Apply to job on the pack) to create a draft plan.
  3. Submit definition, then someone else with the appointment clicks Approve definition.
  4. Record Inspections & Tests with evidence; the reviewer Accepts or Rejects; fix failures with a Nonconformance and Record retest.
  5. Issue quality release when nothing blocks, then Job Quality Report → Issue PDF and file.

Worked example: Pump overhaul at a customer's plant​

  • Job site: the customer's plant address (this sets the jurisdiction).
  • Packs: [NZ] Pumps and pumping systems, plus Welding and metal fabrication if you weld.
  • Hold points: scope and edition basis; health, safety and isolation controls; final certification records and handover.
  • Evidence: test sheets, photos, the calibrated instrument used and the Isolation Certificate.

Linked features​

  • Maintenance Compliance: Isolation Certificates and the Maintenance Compliance Report sit beside QC; QC does not replace them.
  • Equipment: Equipment Dossiers, Technical Certificate Reviews and Calibration Evidence under Quality Control → Inspections & Equipment.

Starter packs for Engineering Maintenance​

Mechanical maintenance and machinery overhaul, Pumps and pumping systems, Hydraulic machinery systems, Pneumatic systems and compressed air, Rotating equipment and condition monitoring, Conveyors and material handling, Machine guarding and energy isolation, Lifting equipment and rigging, Cranes hoists and winches, Pressure vessels and receivers, Boilers and steam systems, Process piping and pipework, Mobile plant and heavy equipment maintenance, Shutdown turnaround and restoration, HVAC ventilation and air handling, Refrigeration and heat pumps.

note

JobLink records your quality process and evidence. It does not certify compliance or approve anything by itself. Not legal advice.

Full guide​

Open Quality Control — Engineering Maintenance (PDF)