Quality Control — Building Construction

Preview
This guide is a preview for review. It is not yet approved for publication.
Building ConstructionNZ and AUEnterpriseCustomer package, 20 Nov 2026
Download PDFThe full guide is in the PDF. This page summarises it so you can search and read on a phone.

How quality control works​

Requirements → Trade pack → Job quality scope → Job quality plan → Inspections & tests → Nonconformances → Quality release → Job Quality Report PDF.

Hold points must be accepted before work goes past them; witness points invite someone to attend; review points check documents or competence. The person who accepts an inspection or approves a plan can't be the person who did it.

Why every trade pack shows Draft​

The library ships 50 packs per jurisdiction (NZ, VIC, NSW, QLD, WA, SA, ACT) as drafts on purpose: their requirements still say Unselected edition, many lines say DRAFT criterion for domain review, and nobody has a reviewer appointment yet. Activate only the packs for work you really do, after a competent person reviews them.

Activate a trade pack​

  1. Give the role: Settings → Users → the reviewer → Quality Control: Requirement reviewer.
  2. Record the appointment: Quality Control → Administration → Reviewer appointments → New (user, company, jurisdiction, valid from / until, verification reference).
  3. Activate the requirements first: Quality Control → Planning → Requirements; set the actual edition, effective date, source and evidence, then Review and activate.
  4. Review the pack: Planning → Industry Templates (Quality Trade Packs). Replace DRAFT criterion… text, set the sampling basis, fill the Domain validation tab.
  5. Review and activate the pack. To change it later, use New revision.

Signing on a job also needs a Quality operation appointment for that job (Administration → Quality operation appointments).

Use it on a job​

  1. Quality scope tab on the job: choose the actual Quality work site.
  2. Use pack from the suggestions (or Apply to job on the pack) to create a draft plan.
  3. Submit definition, then someone else with the appointment clicks Approve definition.
  4. Record Inspections & Tests with evidence; the reviewer Accepts or Rejects; fix failures with a Nonconformance and Record retest.
  5. Issue quality release when nothing blocks, then Job Quality Report → Issue PDF and file.

Worked example: Concrete slab pour​

  • Job site: the building site address. Fill the building fields on the Quality scope tab: code edition, volume / pathway, consent or permit date, design date and the approved transition basis.
  • Pack: [NZ] Concrete formwork placement and curing (with Reinforcing steel and embedded items).
  • Lines: approved specification and pour plan (review); pre-pour inspection and delivery records (witness); test results, curing and engineer review (hold); certification records and handover (hold).
  • Council or certifier inspections are recorded as evidence. JobLink does not replace them.

Linked features​

  • Consent / permit details: the building fields on the job's Quality scope tab tie the plan to the code edition and dates that apply.
  • Contractual Concessions: records a customer-approved deviation; it never waives a statutory or safety requirement.

Starter packs for Building Construction​

Structural steel erection and bolting, Civil earthworks and site preparation, Excavation trenching and temporary works, Concrete formwork placement and curing, Reinforcing steel and embedded items, Carpentry and timber framing, Light steel framing and metal systems, Masonry brickwork and blockwork, Roofing cladding and external envelope, Waterproofing membranes and wet areas, Windows glazing and external doors, Insulation plasterboard and internal linings, Passive fire protection and penetrations, Interior fitout tiling flooring and joinery, Scaffolding access and work at height, Demolition and deconstruction, Asbestos and hazardous-material remediation, General building construction and final handover.

note

JobLink records your quality process and evidence. It does not certify compliance or approve anything by itself. Not legal advice.

Full guide​

Open Quality Control — Building Construction (PDF)